INSTALLATION OF SOLAR PANELS AND INVERTER.

The project required a well detailed analysis of the power requirements of the building and an on the grid system was adopted.

An initial load sepration was done on the building to allow for optimal efficiency of the system.

Inverter Rating: 3.5KVA

Battery Bank: 8 Batteries (48 Volts)

Battery Specs: Mercury 12V 200Ahr